The LASTO®STRIP linear bearings are installed according to the following procedure:
Step 1
Substrate preparation After installing the slab formwork, a horizontal substrate preparation of 10-15 mm mortar smooth coat must be created on the top of the wall. This smooth finish must be subtracted from the upper edge of the "formwork" minus the "plan" bearing thickness.
Step 2
Installation The LASTO®STRIP linear bearings are supplied ready for installation and can be laid on the dried smooth screed. The bearings are butt-jointed and the butt joints are masked with adhesive tape.
Step 3
Cable ducts Cut out penetrations and cable ducts in the bearing cleanly and strip the insulation with LASTO®ISOPIPE. Seal the transition to the bearing with adhesive tape. Rigid connections between ceiling and wall must be avoided at all costs.
Step 4
Reworking After stripping the formwork, any concrete residue on the longitudinal edges of the floor bearing must be removed to ensure that the bearing functions properly. Forming the separating cut (see picture) in the subsequent plastering is part of the professional construction of the ceiling bearing.